In July 2016, SUEZ signed a contract for the design, construction and operation of a state-of-the-art wastewater treatment plant with the provision of financing.
Recruitment of personnel with the provision of a 5-year employment and salary guarantee.
33
years
length of contract
2019
commissioning of the new treatment plant
47
million PLN
investment cost
3
years
period of construction of the new plant
2
million m3
of water treated per year